| Re: Mystery car Simon,
They will be producing cars by the end of July 2008 if not sooner. I 've done so many model changes and ramp ups it's not funny. It will take between 90 to 120 days to reach full production. They will be only running one shift so it may be even sooner. I don't know the line speed or JPH as of yet. They usualy build Pilots for test and engineering ,MVSS, crash test, and proving grounds. Then fill the dealer orders first 1 to 2 cars per dealer for all North America. The cars you see now are hand built out of Detroit from one of the Tech Centers. The 2008 model release is usualy in Sept of this year.
Dave |